Duke Point Marine

The project included; demolition of existing barge berth structures including concrete abutments and buried anchor structures; bulk excavation of approximately 34,000m3 of fill, with approximately 20,000m3 under water by means of 750 excavator with long-reach boom and GPS controlled operation; off-site disposal of surplus materials, following screening operations; excavation and placement of aggregates for construction of new barge ramp abutments; production in Northwest Bay Quarry of approximately 7,500m3 of riprap and filter rock armouring, and placement to design grade of all rock armour products on new design slopes.

Key Project Information

  • Project Type:
  • Budget:
    $3.4M
  • Timeline:
    Completed July 2017
  • Client:
    Ruskin Construction LTD