Baffinland Mine Development
Glacier Blasting & Shoring was contracted for an iron mine development on Baffin Island, Nunavut. The project entailed constructing a 100km tote road between the mine and the shipping port. Three drill rigs, transported from Yellowknife by Hercules transport planes, operated 24/7 throughout the project.
Key Project Information
- Project Type:
- Location:Baffin Island, NU
Key Stats:
- Drilled hole depths: 1.5m to 10m
- Project duration: Two springs and two summers
- Blasts: Every second day, moving 7,000 m³ of rock per blast
- Local workforce: 20% of the team
The project was completed without safety incidents and complied with all local regulations, employing significant local labour.