Baffinland Mine Development

Glacier Blasting & Shoring was contracted for an iron mine development on Baffin Island, Nunavut. The project entailed constructing a 100km tote road between the mine and the shipping port. Three drill rigs, transported from Yellowknife by Hercules transport planes, operated 24/7 throughout the project.

Key Project Information

  • Project Type:
  • Location:
    Baffin Island, NU

Key Stats:

  • Drilled hole depths: 1.5m to 10m
  • Project duration: Two springs and two summers
  • Blasts: Every second day, moving 7,000 m³ of rock per blast
  • Local workforce: 20% of the team

The project was completed without safety incidents and complied with all local regulations, employing significant local labour.