YCG Taxiway and Apron Rehabilitation
Copcan Civil LP successfully completed the Castlegar Airport (YCG) Apron Expansion Project, delivering critical upgrades and repairs to the airport’s infrastructure. This project supports enhanced airport operations by providing improved stormwater management, paving, and airfield lighting.
Key Project Information
- Project Type:
- Budget:$5M
- Timeline:Completed September 2024
- Client:City of Castlegar
- Location:Castlegar, BC
Scope of Work:
- Construction of a new apron expansion area, including excavation, granular sub-base course (GSBC), granular base course (GBC), and asphalt paving.
- Installation of 6 new concrete panels and a surrounding transition slab.
- Removal and replacement of trench drains.
- 60mm mill/pave of the existing apron with new line painting.
- Moving and installation of updated airfield lighting and signage.
Challenges & Solutions:
The project required careful coordination of paving operations, stormwater improvements, and airfield lighting installations. By employing precise project management and skilled crews, Copcan ensured on-time delivery without disrupting airport operations.
Overall Impact:
Completed in September 2024, the apron expansion improves operational efficiency and safety at Castlegar Airport, supporting the City of Castlegar’s ongoing infrastructure upgrades.