Skip to content
  • About Norland
    • About Norland
    • Health & Safety
    • Corporate Responsibility
    • NorLand News
  • Services
  • Projects
  • Contact Us
Careers
Site Search
  • About Norland
    • About Norland
    • Health & Safety
    • Corporate Responsibility
    • NorLand News
  • Services
  • Projects
  • Contact Us
Careers
Johnson St Bridge

Johnson St Bridge

  • 19 June 202428 October 2024
  • by Ellie Elmi

Scope of Work

Our team installed 1830mm diameter casings with 25mm wall thickness, up to 33m long, through 18m of overburden into 340mPa granite rock. A 7m deep rock socket was completed below the casing tip. Due to the undulating bedrock profile, with grade differences of 2.2m across the casing diameter, pipe piles were fabricated on-site with cutting teeth and passed to a 160-ton crane on the work platform. The pier piles’ cut-off elevation was 3m below low water, necessitating a specially designed reinforcing cage suspension bracket to support splicing and concrete pouring. All concrete used was 45 mPa, tremie poured.

To excavate overburden, we employed a Leffer LKG1-180 Spherical grab, directly disposing of material into trucks. For seating the steel casing into bedrock and completing the 7m deep sockets, we utilized a Wirth PBA 612 Pile Top drill with a reverse-flood drilling system, recycling water through containment tanks.

Challenges & Solutions

The project’s primary challenge was maintaining installation accuracy, critical due to the pier substructure’s method. We achieved precision with all piles installed within 35mm of design position and 0.5 degrees of vertical. The rest pier, intermediate pier, and east abutment were supported by 1220mm diameter piles drilled through overburden, seated into bedrock, and completed with 3-5m rock sockets, reinforced and tremie concreted as specified.

Utilizing a Nissha RT150 rotator and Down-hole Hammer reverse-circulation drilling system, we managed tailings through a closed loop, ensuring clean and efficient operations. Each pile was flushed with fresh water and inspected via video to meet strict quality standards.

Overall Impact

This project exemplified CDI’s ability to deliver high-quality, precise construction in challenging conditions. Our innovative methods and dedication to excellence ensured the successful completion of the Bascule pier, reinforcing our reputation as a leading specialty foundation contractor.

GM Shrum Transformer Delivery

GM Shrum Transformer Delivery

  • 19 June 202417 July 2024
  • by Ellie Elmi
Rail Transload, Transportation and Offloading Services Case Study for ABB Power

Rail Transload, Transportation and Offloading Services Case Study for…

  • 19 June 202423 September 2024
  • by Ellie Elmi

Scope of Work: The transformers, each weighing 107 metric tonnes, were delivered by rail to Revelstoke, BC. Apex used a jack and roll system to transfer the units from rail cars onto a dual-lane trailer. Two Western Star tractors—one pulling and one pushing—transported the transformers to the Mica Dam site. The route required a professional engineering evaluation of all bridges and road culverts to ensure the safe transport of the oversized and overweight loads. En route, three pilot cars guided the convoy, maintaining radio communication to ensure safety and adherence to MOT regulations. Upon arrival, the transformers were offloaded using the dam’s 300-ton gantry crane and positioned at the final site.

Challenges & Solutions: The project presented several challenges, including the sheer weight of the transformers, the need for specialty trailers, the remote and rugged location, and navigating public highways with oversized loads. Additionally, the project had a strict timeline due to weather conditions. Apex overcame these challenges by deploying the correct trailer equipment, assembling a skilled crew of movers, and working with a professional engineering firm to design an efficient and safe delivery route. The crew navigated the complex logistics, ensuring timely delivery without compromising safety or quality.

Overall Impact: This two-month project was completed on schedule, with all transformers delivered safely and without incident. The successful transportation of these transformers played a vital role in the Mica Dam upgrade, helping to significantly increase power generation capacity and provide reliable energy to tens of thousands of homes during peak periods. Apex’s expertise and precise execution contributed to the overall success of this critical infrastructure project.

Tretheway Creek Run of the River Project Transformer Delivery

Tretheway Creek Run of the River Project Transformer Delivery

  • 19 June 202417 July 2024
  • by Ellie Elmi
Decommissioning of VIT Transformers Case Study

Decommissioning of VIT Transformers Case Study

  • 19 June 20242 August 2024
  • by Ellie Elmi
Western Alberta Transmission Line

Western Alberta Transmission Line

  • 18 June 20242 August 2024
  • by Ellie Elmi
Trans-Canada Highway Fan Drain Installation

Trans-Canada Highway Fan Drain Installation

  • 18 June 20242 August 2024
  • by Ellie Elmi
Keith Road Bridge Replacement

Keith Road Bridge Replacement

  • 18 June 20242 August 2024
  • by Ellie Elmi
Surrey Memorial Hospital Tunnel Installation

Surrey Memorial Hospital Tunnel Installation

  • 18 June 202421 October 2024
  • by Ellie Elmi
Great Northern Way Campus – Lot P

Great Northern Way Campus – Lot P

  • 18 June 202420 September 2024
  • by Ellie Elmi

Scope of Work:

NorLand partnered with BAUER Foundations Canada to install a temporary secant pile wall along the former False Creek shoreline, with piles ranging from 9.6 to 15.7m, embedded 2m into bedrock. Additional shotcreting and value-engineered tie-back anchors were used to reduce costs and time.

Challenges & Solutions:

The excavation site presented challenges due to the fine silt and clay of the former creek bed. NorLand addressed these by utilizing swamp pads for tie-back installation and shotcreting areas with shallow bedrock elevations to achieve cost savings.

Overall Impact:

NorLand’s contributions to this high-profile development improved project efficiency and reduced costs, helping to shape a key hub in Vancouver’s future transportation and commercial landscape.

Posts pagination

1 … 4 5 6 7 8 … 23
Back to Top
  • About NorLand
  • Services
  • Projects
  • Contact Us
  • Careers
Privacy Policy
PO Terms & Conditions

© Copyright 2025 NorLand Limited

Site by Red Rocket Creative Strategies