The project included; removal of existing 140 metre long multi-component retaining wall and replacement with a cast-in-place concrete structure; excavation of 1 lane of Hwy 3B/22 and Upper Columbia Road to accommodate removal of stacked rock and bin wall parts; placement of new cast-in-place concrete footing and wall and re-established of both Hwy 3B/22 and Upper Columbia Road.

Key Project Information

  • Project Type:
  • Budget:
    $2.2M
  • Timeline:
    Completed December 2016
  • Client:
    Ministry of Transportation and Infrastructure