Parsons Creek East Arterial Interchange
Project Overview:
H Piles were ordered to meet the requirements of Spec CSA G40.21M 350W. Pile locations were marked with offsets. Inspections and approvals of splices and driving criteria were established. The Birmingham Lead System was used to ensure horizontal and vertical positioning. A D30-42 Hammer was used to drive until refusal. PDA-EOID testing was performed after the driving was finished. A 10,000 lb. Drop Hammer was used on any piles that required re-striking. Once seated, the piles were cut off to the required elevations. The pier piles were 1200mm dia bell piles to approx. 12lm deep each, the overburden material was saturated wet sandy clay. The casings were taken to bedrock and seated, the bedrock was clay shale. The bell was drilled below the casing tip to a diameter of 8’ (2/1 bell).
Key Project Information
- Project Type:
- Budget:$600K
- Timeline:March to July 2014
- Client:Innovative Civil Constructors Inc