Rock Bay Remediation Project

Supply and install 73.51 lm of 1200mm diameter secant pile wall with an average total depth of 15.94m with a 500mm embedment into rock. A total of 78 each secant piles with a 950mm center to center distance complete with 59 each W610 x 140 x 15 to 18m long beams from P1 to P47 and 26 each W610 x 110 x 15m long beams from P48 to P74. 4 secant piles are only concrete filled. Included is the supply and delivery of 8-10 MPa concrete.

Key Project Information

  • Project Type:
    Shoring Walls, Cofferdams, and Cutoff Walls
  • Budget:
    $1.5M
  • Timeline:
    3 months
  • Client:
    Salish Sea Industrial Services
  • Location:
    Rock Bay, BC