Memorial Avenue Upgrades Phase 1

The project included; installation of 950 metres of storm sewer piping ranging in size from 250-600 mm diameter; construction of an asphalt bike path approximately 340 metres long and 3 meters wide, and construction of bio-swales and installation of street lighting.

Key Project Information

  • Project Type:
  • Budget:
    $1M
  • Timeline:
    Completed May 2017
  • Client:
    Town of Qualicum