Transformer and Switch Gear Installation

Pro-Tech Industrial Movers recently executed a critical project involving the relocation and installation of a 3000KV transformer and switch gear sections into an electrical room. This complex task was part of a broader development in the Lower Mainland, BC, and required meticulous coordination and logistical planning.

Key Project Information

  • Project Type:
    Machinery Moving
    Pre-Planning Logistics
    Project Consulting
  • Budget:
    $
  • Timeline:
  • Client:
    Molnar Group

Scope of Work:

  • Machinery Moving: Transported the 13,200-pound transformer core and coil from on-site storage to the installation site.
  • Crane Coordination: Hoisted the transformer with a Hiab at a 40’ radius and Kasen Crane at a 95’ radius through multiple floor slab openings with less than 6” clearance.
  • Skating and Placement: Skated the transformer and switchgear sections approximately 200’ into the electrical room, navigating multiple slopes and overhead obstructions with less than 2” clearance.
  • Assembly: Collaborated with site electricians to assemble the components and place the transformer onto vibration isolators.

Challenges & Solutions:

  • Site Logistics: Managed a spread-out site over three city blocks, coordinating multiple stakeholders.
  • Restricted Access: Navigated narrow roads and multiple slopes within the parkade.
  • Clearance Issues: Ensured precise movement with minimal clearance, highlighting Pro-Tech’s expertise in tight space operations.

Overall Impact:

This project underscores Pro-Tech Industrial Movers’ proficiency in machinery moving, logistical planning, and project consulting. The successful installation of the transformer, despite significant challenges, demonstrates Pro-Tech’s commitment to precision, safety, and efficient project management.