

The 1st phase started with the construction of the east river pier and installing 5 each 1500mm diameter concrete caissons 14m deep. They were excavated using a temporary casing installed to pile tip. The very dense clay shale bedrock (N100+) would not seal off and all piles were poured using tremie concrete procedures. The temporary casing was extracted as the concrete was tremied. Caissons were tested for H2S gas during the entire drilling process.
The east abutment was also installed in the 1st stage with -35 degree weather.
During the spring of 2012, the berm installed to support the installation of the girders, flooded due to extremely high water levels. Sheet piles were installed to reinforce the berm cofferdam as extra work.
The second stage work started in September, 2012 with the installation of the west abutment h-piles. Excavation for the 3rd pier was completed after the abutment piles were driven. 5 each 1500 mm diameter shafts were completed at the third pier. The drill rig and crew moved from the 3rd pier to the 2nd pier and the shafts were installed. All shafts were wet and tremie concrete procedures were used to complete the shafts.
Our team installed piles ranging from 610mm to 3000mm in diameter for bridge piers, stabilization piles, and deep support piles through abandoned coal mines. Key components included:
The Anthony Henday Project exemplifies CDI’s capability to manage large-scale infrastructure projects under challenging conditions. Our innovative techniques and commitment to safety ensured the successful completion of this critical development, enhancing Edmonton’s transportation infrastructure and demonstrating our leadership in the specialty foundation industry.