Skip to content
  • About Norland
    • About Norland
    • Health & Safety
    • Corporate Responsibility
    • NorLand News
  • Services
  • Projects
  • Contact Us
Careers
Site Search
  • About Norland
    • About Norland
    • Health & Safety
    • Corporate Responsibility
    • NorLand News
  • Services
  • Projects
  • Contact Us
Careers
Mosaic Civil Works

Mosaic Civil Works

  • 14 August 202428 October 2024
  • by Ellie Elmi

Scope of Work:

The project involved the construction of two separate buildings on adjacent lots. This work encompassed 11,000 m³ of bulk excavation, detailed footing excavation, under slab trenching, perimeter drain installation, slab-on-grade preparation, and the installation of both onsite and offsite utilities.

Onsite utilities included water service installation, sanitary works, and storm works, which featured the construction of three rock pits. Additionally, the project required the installation of onsite lighting and BC Hydro infrastructure, including a PMT and concrete encasement as necessary.

The Onsite scope of work also covered the preparation and installation of hardscaping elements, such as paving, sidewalks, and curb and gutter systems, as well as the preparation of softscape areas.

The offsite scope of work involved the removal and replacement of 1,200 m² of concrete sidewalk, 450 meters of concrete curb and gutter, and 1,400 m² of asphalt. Additionally, it included drainage upgrades, tying in new building services (water, storm, and sanitary) to municipal mains, and rerouting Hydro and Telus lines to move power and Telus services from overhead to underground. The project also encompassed the installation of offsite street lighting.

Challenges & Solutions:

Highstreet approached Copcan to tender the project in July 2022, despite the drawings not being fully complete and some aspects missing. Following the tender close, Copcan collaborated with Highstreet to ensure the project could proceed according to their schedule. Copcan continued to work closely with Highstreet as IFC (Issued for Construction) drawings were developed during the construction stage, maintaining both the project schedule and high-quality standards.

The offsite works occurred on municipal roadways, with one road being the main highway through Parksville. Copcan manages traffic control with the City of Parksville and Highstreet while completing the work with no incidents.

Scheduling was a challenge on this project, as two separate buildings were being constructed simultaneously, each with slightly different timelines and trade schedules. Copcan coordinated closely with Highstreet’s superintendent and other sub-trades on site to ensure that the schedule was maintained for both buildings. Despite these challenges, the project finished on schedule.

Overall Impact:

Construction began in the summer of 2022 and was completed in November 2023. Copcan completed the contract work on schedule and was awarded additional work during construction that was not included in the original scope. Copcan worked collaboratively with sub-trades, local municipalities, and Highstreet’s superintendent to bring the project to completion, ensuring the satisfaction of all parties involved.

Western Grater Contracting

Western Grater Contracting

  • 4 April 202312 November 2024
  • by main_admin
Bowen Road Rehabilitation

Bowen Road Rehabilitation

  • 14 August 202428 October 2024
  • by Ellie Elmi
Harmac Pacific Riverwater Pipeline

Harmac Pacific Riverwater Pipeline

  • 14 August 202428 October 2024
  • by Ellie Elmi

HDPE pipe was staged a month in advance of the in-line replacement shut down window and fusing was completed two week prior to the shutdown. Copcan crews worked seven consecutive days putting in 12-15 hour shifts in order to complete the installation within the allocated time. Installation was complete one day early.

In addition to the fusing and installation of the HDPE pipe there was also the cutting and welding of two new steel transition spools at the tie-in points complete with flanged connections and paint coating. Once the installation was complete, the HDPE pipe was buried with fill and hydroseeded.

Inclusive/Accessible Washrooms

Inclusive/Accessible Washrooms

  • 1 August 202428 October 2024
  • by Ellie Elmi
Building Exterior Upgrades

Building Exterior Upgrades

  • 1 August 202428 October 2024
  • by Ellie Elmi
Amphitrite Point Equipment Building and Helicopter Pad

Amphitrite Point Equipment Building and Helicopter Pad

  • 1 August 202428 October 2024
  • by Ellie Elmi
Building Addition and Renovation

Building Addition and Renovation

  • 1 August 202428 October 2024
  • by Ellie Elmi
Miracle Beach Campground Washroom Building Renovation

Miracle Beach Campground Washroom Building Renovation

  • 1 August 202428 October 2024
  • by Ellie Elmi
Alberni Valley Washroom Renovation

Alberni Valley Washroom Renovation

  • 1 August 202428 October 2024
  • by Ellie Elmi

Posts pagination

1 2 3 4 5 … 10
Back to Top
  • About NorLand
  • Services
  • Projects
  • Contact Us
  • Careers
Privacy Policy
PO Terms & Conditions

© Copyright 2025 NorLand Limited

Site by Red Rocket Creative Strategies