South Surrey Interceptor No. 2

South Surrey Interceptor No. 2

  • 10 September 202328 October 2024
  • by main_admin

Scope of Services

The project kicked off with BEL Contracting implementing several facilitating measures, which included the construction of temporary driveways for Panorama Place and the property at 15350 153a Street. Notably, these initial measures also involved the removal of trees and other hardscapes to clear the way for mainline construction. Electrical installations were another crucial aspect of the project’s scope. A dedicated electrical kiosk was set up, along with an antenna pole, both of which were intricately tied in with flow transducers. This level of detail was extended to the installation of conduits for BC Hydro, requiring rigorous coordination to ensure uninterrupted power services and to meet regulatory inspection criteria.

Post-construction restoration was another significant element of the project. Key milestones were achieved in terms of reinstating property access, predominantly focusing on 153a Street and the property at 15350 56 Avenue. Activities in this phase included road repaving, construction of curbs and gutters, line painting, and installation of road signage. At the 15350 56 Avenue property, a modular concrete block retaining wall was erected. Furthermore, landscape restoration work was performed across various sections of the project area, leaving a positive visual impact on the community.

Before declaring the project complete, BEL Contracting undertook the vital task of compiling an exhaustive asset inventory, which was supplemented by operational manuals and detailed technical data. This ensures that future maintenance and operational tasks can be carried out efficiently. To validate the robustness of the new installations, rigorous testing and commissioning processes were employed, guaranteeing that all components either met or exceeded the regulatory and operational standards.

Beyond the engineering and construction aspects, a strong emphasis was placed on risk management to ensure the safety and well-being of everyone involved. This multifaceted project was not merely aimed at improving the city’s sewer system, It was also designed to manage and mitigate a variety of construction risks, ensuring the safety and well-being of all involved.

Thomas Creek Pedestrian Bridge Installation

Thomas Creek Pedestrian Bridge Installation

  • 31 July 202331 July 2024
  • by Kaelan

Scope of Work

Due to limited local availability, the pedestrian bridge was manufactured in Ontario and then shipped across the country. The GIG team assembled the bridge on-site, with an 80-ton crane initially positioning the components and a 500-ton crane completing the final lift. BEL Contracting managed the earthworks, Kingston Construction handled the bridge assembly, and FRPD was responsible for pile driving.

Challenges & Solutions

Transporting the bridge components across the country required meticulous logistics planning, ensuring all parts arrived on-site in perfect condition. The GIG partnership allowed for seamless collaboration, with each partner bringing their expertise to ensure the project was executed smoothly despite its complexity.

Overall Impact

The successful installation of the Thomas Creek Pedestrian Bridge not only facilitates pedestrian access but also supports future development by accommodating a water main underneath, which is crucial for the expanding subdivision. This project highlights GIG’s ability to manage and execute complex infrastructure projects efficiently and effectively.

Posts pagination

1 2
Back to Top
  • About NorLand
  • Services
  • Projects
  • Contact Us
  • Careers
Privacy Policy
PO Terms & Conditions

© Copyright 2025 NorLand Limited

Site by Red Rocket Creative Strategies